🔥 Ampacity & Derating Check
Start with the insulation column, correct for heat and bundled conductors, then see exactly which safety limit controls.
Conductor-side derating
The two factors multiply the insulation-column ampacity first. Only after that do the termination and small-conductor limits apply.
Binding limit:
Derating after ambient correction and conductor adjustment 110.14(C) termination temperature limit 240.4(D) small-conductor capLoad-side check — separate calculation
Continuous-load sizing and conductor derating answer different questions. The 125% rule sizes the circuit for a long-running load; it is not multiplied into the conductor derating factors.
The entered load is within the final permitted ampacity.
The entered load is above the final permitted ampacity.
The separately calculated continuous-load requirement is within the final permitted ampacity.
The separately calculated continuous-load requirement is above the final permitted ampacity.
What this checks
This U.S. edition uses the verified NEC Table 310.16 base ampacities, Table 310.15(B)(1) ambient factors, Table 310.15(C)(1) conductor factors, 110.14(C) termination limits, and 240.4(D) small-conductor caps. It never interpolates a missing value.
Ampacity and voltage drop are separate checks — a wire must pass both.